Phase 1 Construction includes installing sanitary sewer lines, water mains, and storm drainage. This work will include grading, temporary gravel/driveway access, concrete paving, other miscellaneous concrete work, and restoration.
Traffic Alerts
Updated June 28, 2022
41st Street, Marion Road to I-29
- Paving on Marion Road between 41st Street and 44th Street is complete and reopened to traffic.
- Paving on 41st street began the week of June 20 starting at Marion Road and working toward the east. Intermittent intersection closures will continue as paving progresses.
- The south side of the intersection at 41st Street and Cathy Avenue is reopened. The intersection was previously closed for paving operations.
- The south side of the intersection at 41st Street and Terry Avenue is reopened.
- The south side of the intersection at 41st Street and Gateway Boulevard is closed June 27 through July 1 for paving operations.
- Asphalt and concrete paving on Marion Road South of 41st Street is completed.
- Crews completed grading on 41st Street east of Terry Avenue.
- In July and August, lane closures will go into effect on I-29 with two lanes of traffic remaining open. Crews will begin storm drainage work along I-29 with bridge improvements on the I-29 overpass.
Commuter Route Information
- On Wednesday, July 6, 2022, two-way traffic on 41st Street between Marion Road and Terry Avenue will be shifted to the newly-paved lanes on the south side of 41st Street for roadway removals. One-lane traffic will remain open in each direction on the south side of 41st Street. Left turn lanes will remain open at the intersections of 41st Street and Terry Avenue and 41st Street and Marion Road.
- Marion Road between 41st Street and 39th Street will be reduced to three lanes from Wednesday, July 6, 2022 through Monday July, 11, 2022 in preparation for road reconstruction.
- Marion Road will be closed beginning Monday, July 11, 2022 to traffic between 41st Street and 39th Street for approximately two months for road reconstruction. Drivers are urged to use caution and reduce their speed while traveling through the construction area and consider using alternate routes Sertoma Avenue and 26th Street.
- Motorists should drive through the Marion Road intersection slowly due to the grade change. Use extreme caution when driving through the intersection.
- The outside right turn lane on the southbound Interstate 29 off-ramp onto 41st Street is closed.
- Temporary closures at Gateway Boulevard, Terry Avenue and Cathy Avenue will alternate so that at least one intersection is open at all times.
- Please follow the posted signs around the closures.
- Spring 2022 - Reconstruction of the south side of 41st Street starts at Meadow Avenue and progresses to the west.
- Spring 2022 - Marion Road will be closed south of 41st Street for one month. The detour uses Sertoma Avenue and 57th Street.
- Summer 2022 - Reconstruction of the north side of 41st Street starts at Meadow Avenue and progresses to the west.
- Fall 2022 - Marion Road will be closed north of 41st Street for one month. The detour uses Sertoma Avenue and 26th Street.
- Time frames are all approximate, subject to change, and weather and schedule permitting.
For the latest on road and weather conditions, road closures, construction work zones, commercial vehicle restrictions, and traffic incidents, visit sd511.org or dial 511.
Marion Road Closures & Detours
2022 Spring to Fall
- Spring 2022 - Reconstruction of the south side of 41st Street starts at Meadow Avenue and progresses to the west.
- Spring 2022 - Marion Road will be closed south of 41st Street for one month. The detour uses Sertoma Avenue and 57th Street.
- Summer 2022 - Reconstruction of the north side of 41st Street starts at Meadow Avenue and progresses to the west.
- Fall 2022 - Marion Road will be closed north of 41st Street for one month. The detour uses Sertoma Avenue and 26th Street.
- Time frames are all approximate, subject to change, and weather and schedule permitting.
While Marion Road is closed, business access will be open along Larch Avenue and 44th Street.
Pedestrian Routes
Construction Progress
Construction began in early 2022 and is anticipated to be completed in summer 2024. The project is divided into two phases: west and east. The west half of the project area includes 41st Street from Marion Road to Meadow Avenue. The east half includes 41st Street from Meadow Avenue to Shirley Avenue.
Click or tap on the dots to see more detail about a particular area.

South Side of 41st Street West of I-29 (2022)
Construction progresses on the south side of 41st Street west of I-29.
-
Removals
In ProgressCompleted -
Sanitary Sewer
In ProgressCompleted -
Water Main
In ProgressCompleted -
Drainage
In ProgressCompleted -
Grading
In ProgressCompleted -
Gravel
In ProgressCompleted -
Concrete Paving
In ProgressCompleted -
Misc Concrete
In ProgressCompleted -
Restoration
In ProgressCompleted
Marion Road South of 41st Street (2022)
Construction progresses on Marion Road south of 41st Street.
-
Removals
In ProgressCompleted -
Sanitary Sewer
In ProgressCompleted -
Water Main
In ProgressCompleted -
Drainage
In ProgressCompleted -
Grading
In ProgressCompleted -
Gravel
In ProgressCompleted -
Concrete Paving
In ProgressCompleted -
Misc Concrete
In ProgressCompleted -
Restoration
In ProgressCompleted
North Side of 41st Street West of I-29 (2022)
Construction has not started on the north side of 41st Street west of I-29.
-
Removals
In ProgressCompleted -
Sanitary Sewer
In ProgressCompleted -
Water Main
In ProgressCompleted -
Drainage
In ProgressCompleted -
Grading
In ProgressCompleted -
Gravel
In ProgressCompleted -
Concrete Paving
In ProgressCompleted -
Misc Concrete
In ProgressCompleted -
Restoration
In ProgressCompleted
Marion Road North of 41st Street (2022)
Construction has not started on Marion Road north of 41st Street.
-
Removals
In ProgressCompleted -
Sanitary Sewer
In ProgressCompleted -
Water Main
In ProgressCompleted -
Drainage
In ProgressCompleted -
Grading
In ProgressCompleted -
Gravel
In ProgressCompleted -
Concrete Paving
In ProgressCompleted -
Misc Concrete
In ProgressCompleted -
Restoration
In ProgressCompleted
I-29 Interchange Work (2022-2023)
Construction has not started on the new interchange.
-
Removals
In ProgressCompleted -
Sanitary Sewer
In ProgressCompleted -
Water Main
In ProgressCompleted -
Drainage
In ProgressCompleted -
Grading
In ProgressCompleted -
Gravel
In ProgressCompleted -
Concrete Paving
In ProgressCompleted -
Misc Concrete
In ProgressCompleted -
Restoration
In ProgressCompleted
South Side of 41st Street East of I-29 (2023)
Construction has not started on the south side of 41st Street east of I-29.
-
Removals
In ProgressCompleted -
Sanitary Sewer
In ProgressCompleted -
Water Main
In ProgressCompleted -
Drainage
In ProgressCompleted -
Grading
In ProgressCompleted -
Gravel
In ProgressCompleted -
Concrete Paving
In ProgressCompleted -
Misc Concrete
In ProgressCompleted -
Restoration
In ProgressCompleted
North Side of 41st Street East of I-29 (2023)
Construction has not started on the north side of 41st Street east of I-29.
-
Removals
In ProgressCompleted -
Sanitary Sewer
In ProgressCompleted -
Water Main
In ProgressCompleted -
Drainage
In ProgressCompleted -
Grading
In ProgressCompleted -
Gravel
In ProgressCompleted -
Concrete Paving
In ProgressCompleted -
Misc Concrete
In ProgressCompleted -
Restoration
In ProgressCompleted
-
April - November 2022
41st Street construction from Marion Road to Meadow Avenue (west half of project area)
-
April - November 2023
41st Street construction from Meadow Avenue to Shirley Avenue (east half of project area)
-
April - June 2024
Finishing touches and clean-up; complete construction